Material Sourcing and Qualification

Stage: Specification, Design and Verification

Definition

Before HDR, activities include:

  • Initiate discussions with vendors

Between HDR and PDR, activities include:

  • Participate in BOM development
  • Get component samples

Between PDR and CDR:

  • Get samples tested (R&D and component engineers)
  • Begin qualification process with non-qualified suppliers

Between CDR and Alpha Readiness Review:

  • Component engineers and Commodity Analysts to agree on vendor selection (first/second source)
  • Complete component & vendor qualification
  • Establish approved vendor list
  • Finalize second source qualifications
  • Negotiate contracts with vendors
  • Transmit contracts to Contract Manufacturer

Dependencies

Needs to start as soon as we start talking about BOM

Needs to be completed to ensure that only qualified vendors will be used during

Beta testing step

Input

BOMs

Deliverables

List of qualified vendors

Responsibility

Manufacturing representative in PMT

Resources

Workload

Competencies

Component engineers

Commodity Analystsv

Lead-times

-

Metrics

LT analysis

Improvement plan

Cost and BOM analysis

Material cost reduction plan

Guidelines

Each time a BOM is presented, it has to be with qualified vendors.

Vendor qualification process:

  1. Check whether vendors are already qualified (by Atrica or by sub-contractors)
  2. Run qualification process for non-qualified vendorsComponent qualification procedure